Document Purpose — Provide a single‐source roadmap outlining every major activity, owner, date, and dependency required to deliver a secure, autonomous IT environment by Day 1 and through TSA exit.
Project Overview
- Scope: list key systems, infrastructure, and security components in separation perimeter.
- Objectives: operational continuity, TSA exit in ⟨mm/yy⟩, zero critical incidents.
- Budget: $ ⟨amount⟩ one-time separation spend; $ ⟨amount⟩ annual run-rate.
Governance and Roles
- Program Sponsor: ⟨Name, Title⟩.
- IT Separation Lead: ⟨Name⟩.
- Workstream Owners: ERP ⟨Name⟩; Infrastructure ⟨Name⟩; Security ⟨Name⟩; Data Migration ⟨Name⟩; Vendor Contracts ⟨Name⟩.
- Steering-Committee Cadence: bi-weekly until cut-over; weekly for 30 days post-Day 1.
Key Milestones and Target Dates
- Complete application and infrastructure inventory — ⟨dd/mm/yy⟩.
- Finalise target architecture and budget approval — ⟨dd/mm/yy⟩.
- Sign high-risk vendor novations — ⟨dd/mm/yy⟩.
- Finish mock data migration cycle 2 — ⟨dd/mm/yy⟩.
- Pilot network cut-over at low-risk site — ⟨dd/mm/yy⟩.
- Identity-platform go-live — ⟨dd/mm/yy⟩.
- Production cut-over and Day 1 operations — ⟨dd/mm/yy⟩.
- First TSA exit checkpoint — ⟨dd/mm/yy⟩.
- Final TSA termination and post-implementation review — ⟨dd/mm/yy⟩.
Workstream Activity Checklist
- ERP: licence novation, data migration, interface rebuild, user-acceptance testing, cut-over rehearsal.
- CRM: data extraction, cleansing, SaaS tenancy provisioning, security configuration.
- HRIS & Payroll: employee-master load, parallel payroll, statutory filing validation.
- Infrastructure: procure edge devices, build cloud foundations, deploy SD-WAN, implement monitoring.
- Network Segmentation: allocate new IP ranges, configure firewalls, establish inter-company tunnels, schedule phased decommissioning.
- Identity & Access: create new domain, migrate users and groups, enforce MFA, terminate legacy trusts.
- Security: deploy EDR agents, integrate logs into new SIEM, run penetration test, remediate findings.
- Data Migration: finalise mapping sheets, execute ETL, validate record counts, secure data-destruction certificates.
- Vendor Contracts: complete consent negotiations, sign replacement agreements, update SAM records.
- TSA Management: confirm scope, SLAs, pricing; create exit checklist; monitor performance and ramp-down dates.
Resource Plan
- Internal FTEs required by workstream and month.
- External partners: systems integrator, cloud MSP, data-migration vendor, security tester.
- Contingency pool: ⟨X⟩ percent of total hours for unplanned spikes.
Risk and Issue Log (Top Entries)
- Data-quality defects delaying ERP migration — owner ⟨Name⟩; mitigation: additional cleansing sprint.
- Vendor consent fee escalation — owner ⟨Name⟩; mitigation: bundle contracts, escalate to procurement VP.
- Bandwidth constraints on TSA tunnels — owner ⟨Name⟩; mitigation: procure temporary capacity boost.
Cut-Over Command Centre Plan
- War-room location or virtual bridge details.
- Roster of on-call engineers and decision-makers by hour.
- Go/No-Go criteria for each critical system.
- Escalation ladder up to CIO and Steering Committee.
Post-Day 1 Stabilisation Metrics
- System availability target ≥ 99.8 %.
- First-time-right incident resolution ≥ 95 %.
- TSA service credits ≤ ⟨amount⟩.
- Cyber-incident count = 0.
Populate this template, update weekly, and use it as the authoritative schedule, status, and escalation reference for the entire IT separation programme.
Request the Carve-Out Playbook
Table of Contents:
Table of Contents
1. Introduction and Overview
- 1.1 Purpose of This Playbook
- 1.2 Defining Carve-Outs (Divestitures)
- 1.3 Key Differences Between Carve-Outs and Other M&A Transactions
- 1.4 Common Drivers and Strategic Rationale for Carve-Outs
- 1.5 Overview of the Carve-Out Lifecycle
- 1.6 How to Use This Playbook
2. Strategic Considerations and Decision-Making
- 2.1 Evaluating the Carve-Out Rationale
- 2.2 Assessing Market Opportunities and Timing
- 2.3 Stakeholder Alignment and Governance
- 2.4 Risk Assessment and Mitigation Strategies
- 2.5 High-Level Financial Considerations
- 2.6 Sample Template: Carve-Out Feasibility Study
- 2.7 Checklist: Key Questions to Ask Before Deciding on a Carve-Out
3. Planning the Carve-Out Program
- 3.1 Establishing the Carve-Out Program Management Office (PMO)
- 3.2 Defining Scope and Objectives
- 3.3 Organizational Structure and Key Roles
- 3.4 Timeline Development and Milestone Planning
- 3.5 Resource Planning and Budgeting
- 3.6 Program Governance and Steering Committees
- 3.7 Tools and Templates: Carve-Out Project Charter and Planning Documents
- 3.8 Step-by-Step Guide: Setting Up the PMO
4. Financial Analysis and Preparation
- 4.1 Developing Carve-Out Financials (Pro Forma Statements)
- 4.2 Allocating Corporate Overheads
- 4.3 Working Capital Adjustments and Cash Management
- 4.4 Tax Implications and Structuring
- 4.5 Valuation Approaches for the Carve-Out Entity
- 4.6 Checklist: Financial Data Requirements
- 4.7 Template: Standalone Cost Analysis
5. Operational Separation and Target Operating Model (TOM)
- 5.1 Defining the Future State Organization
- 5.2 Critical Business Functions to Separate
- 5.3 Retained vs. Transitioned Capabilities
- 5.4 Cross-Functional Dependencies
- 5.5 Service Level Agreements and Transition Services
- 5.6 Template: Target Operating Model Blueprint
- 5.7 Step-by-Step Guide: Designing Your TOM
6. Legal and Regulatory Framework
- 6.1 Understanding Legal Entities and Corporate Structures
- 6.2 Regulatory Approvals and Filings
- 6.3 Contract Assignments and Renegotiations
- 6.4 Employee and Labor Law Considerations
- 6.5 Antitrust and Competition Law Considerations
- 6.6 Securities and Exchange Requirements (If Applicable)
- 6.7 Sample Template: Legal Due Diligence Checklist
7. Human Capital and Organizational Readiness
- 7,1 Workforce Mapping and Allocation
- 7.2 Talent Retention and Employee Engagement
- 7.3 Compensation and Benefit Alignments
- 7.4 Cultural Considerations and Change Management
- 7.5 Checklist: HR-Related Actions for Day 1 Readiness
- 7.6 Step-by-Step Guide: Conducting Workforce Transfers
8. Technology and IT Separation
- 8.1 IT Carve-Out Strategy and Guiding Principles
- 8.2 Inventory of Applications and Infrastructure
- 8.3 Data Migration and Security
- 8.4 Network and Systems Separation
- 8.5 Third-Party Vendor Contracts and Licensing
- 8.6 Checklist: Key IT Systems and Separation Activities
- 8.7 Sample Template: IT Separation Work Plan
9. Communication and Stakeholder Management
- 9.1 Communication Strategy and Governance
- 9.2 Internal Stakeholder Mapping
- 9.3 External Stakeholders: Investors, Clients, and Suppliers
- 9.4 Media Relations and Public Announcements
- 9.5 Message Alignment and Consistency
- 9.6 Change Management and Cultural Integration
- 9.7 Template: Comprehensive Communication Plan
10. Day 1 Readiness Planning
- 10.1 Defining “Day 1” Scope and Objectives
- 10.2 Critical Systems and Operational Checklists
- 10.3 Transition Services Agreements (TSA) Setup
- 10.4 Compliance and Regulatory Obligations
- 10.5 Business Continuity Plans
- 10.6 Template: Day 1 Checklist
- 10.7 Step-by-Step Guide: Ensuring Operational Continuity
11. Transition Services Agreements (TSAs)
- 11.1 Purpose and Structure of TSAs
- 11.2 Key TSA Terms and Service Level Definitions
- 11.3 Pricing and Cost Allocations
- 11.4 Governance and Conflict Resolution Mechanisms
- 11.5 Exit Strategy and TSA Sunset Provisions
- 11.6 Checklist: TSA Negotiation Points
- 11.7 Sample Template: TSA Master Document
12. Carve-Out Implementation and Execution
- 12.1 Integrated Project Plan for Separation
- 12.2 Managing Parallel Workstreams
- 12.3 Risk Management and Issue Resolution
- 12.4 Real-Time Reporting and Steering Committee Updates
- 12.5 Escalation Procedures and Decision Rights
- 12.6 Checklist: Weekly and Monthly Reporting Templates
- 12.7 Step-by-Step Guide: Project Execution Best Practices
13. Post-Close Stabilization and Operational Handover
- 13.1 Post-Close Governance and Operational Setup
- 13.2 TSA Management and Transition Offloading
- 13.3 Synergy Realization and Cost Management
- 13.4 Performance Tracking and KPIs
- 13.5 Revisiting the Target Operating Model
- 13.6 Checklist: Stabilization Milestones
14. Integration or Standalone Acceleration
- 14.1 Evaluating Long-Term Strategic Options
- 14.2 Standalone Strategy vs. Full Integration
- 14.3 Operational Maturity Roadmap
- 14.4 Value Creation Levers and Growth Opportunities
- 14.5 M&A Opportunities and Bolt-On Acquisitions
- 14.6 Checklist: Building Momentum Post-Carve-Out
15. Lessons Learned and Best Practices
- 15.1 Common Pitfalls and How to Avoid Them
- 15.2 Key Success Factors for Carve-Out Transactions
- 15.3 Industry-Specific Considerations
- 15.4 Checklist: Continuous Improvement for Future Carve-Outs