1. What Is System Advisor Model (SAM)?
The System Advisor Model (SAM) is free software that combines energy-system performance simulation with financial analysis. Strictly speaking, it is a techno-economic decision-support tool, not a conventional management framework. It estimates how an energy installation will operate and what those operating results mean financially.
For executives evaluating renewable power generation, SAM helps connect equipment choices, energy production, operating costs, and commercial arrangements. Consultants can use it to structure a concrete question: which project configuration creates the most attractive economics under credible operating and financing assumptions? Its coverage includes solar, wind, geothermal, and battery-storage applications, among other technologies.
2. Origin and Background
SAM was developed in 2005 by the National Renewable Energy Laboratory (NREL), collaborating with Sandia National Laboratories, initially for internal analysis by the U.S. Department of Energy’s Solar Energy Technologies Program. Its first public release, in August 2007, was called the Solar Advisor Model and covered photovoltaic and concentrating solar power systems.
The name changed to System Advisor Model in 2010 as non-solar technologies were added. Its original purpose—evaluating how technical improvements affect energy economics—expanded into project-design and commercial-feasibility analysis. The laboratory now operates as the National Laboratory of the Rockies (NLR). SAM’s institutional origin matters: it is an engineering and economic modeling platform, rather than a consulting firm’s proprietary methodology.
3. How System Advisor Model (SAM) Works
The name is descriptive, not a three-stage methodology:
- S — System: The energy installation being evaluated.
- A — Advisor: Information supporting an investment or operating decision.
- M — Model: Mathematical representations of performance and economics.
SAM’s analytical architecture pairs a performance model with a financial model. Analysts choose both, populate their inputs, and simulate the case. This pairing is essential: identical equipment can produce different investment outcomes under different tariffs, ownership structures, and financing assumptions.
Performance model: from resource to usable energy
The performance model translates resource conditions and equipment characteristics into energy output. For photovoltaic systems, relevant inputs include weather, array design, equipment, and losses. Battery configurations add charging and discharging behavior, efficiency, operating limits, degradation, and replacement assumptions. The executive question is not simply “How much electricity?” but “When is electricity available, and what operating constraints affect its value?”
Financial model: from energy to economic value
Behind-the-meter projects create value principally through changes in the customer’s electricity bill. Front-of-meter projects can earn revenue through electricity sales, including power purchase agreements (PPAs). SAM’s financial models calculate metrics such as net present value (NPV), internal rate of return (IRR), and levelized cost of energy (LCOE), depending on the configuration. Certain PPA models can calculate either returns at a specified electricity price or the price needed to achieve a target return.
Scenario analysis: from one forecast to a decision
Parametric simulations compare outcomes as inputs change; stochastic analysis varies inputs using specified probability distributions. These capabilities help test design and financial assumptions. They do not make the assumptions correct. Use comparable site-design-commercial cases, rather than comparing unrelated technology labels or headline returns.
4. When to Use System Advisor Model (SAM)
SAM is especially useful when a team can define plausible project alternatives and wants to understand how technical choices influence financial outcomes. Suitable questions include:
- Should a solar project include storage, and at what size?
- Which equipment configuration improves economics rather than merely increasing generation?
- What electricity-sales price supports the required investment return?
- How sensitive are customer savings to load patterns and tariff design?
The required inputs normally include resource data, equipment specifications, capital and operating costs, financial assumptions, and applicable electricity prices. Behind-the-meter analysis also needs customer load data; tariffs can include time-of-use energy charges, demand charges, and export compensation.
For distributed energy developers, begin with individual customer meters and installations. Assess aggregation contracts, communications, and participation requirements separately before extrapolating site-level results into a fleet business case.
Given SAM’s project focus, supplement it when the decision requires network power-flow analysis, system-wide resource planning, or regulated revenue-requirement analysis. A screening workshop can proceed once validated cases exist; investment approval requires deeper engineering, commercial, and financial review. The limiting factor is usually input quality and agreement on assumptions, not running the simulation.
5. How to Apply System Advisor Model (SAM): Step-by-Step
Clarify the decision and scope. Specify the investment decision, evaluation horizon, geography, ownership perspective, and revenue mechanism. Distinguish developer returns, customer savings, and utility-system benefits; these are not interchangeable objectives.
Gather and validate inputs. Obtain resource files, equipment data, quotations, operating-cost estimates, financing assumptions, and contracts or tariffs. For customer-sited projects, reconcile interval load data and tariff calculations against actual bills before modeling savings.
Define comparable units of analysis. Create a case for each site, equipment configuration, operating policy, and commercial structure. Keep common assumptions consistent so differences reflect deliberate choices rather than accidental input changes.
Construct the model and comparison artifact. Select compatible performance and financial models. Replace defaults with project-specific inputs. Preserve the SAM files, input register, software version, and a comparison table containing energy, cash-flow, and decision-relevant financial outputs.
Inspect operations before interpreting returns. Examine generation, charging, discharging, imports, and exports at relevant time intervals. Investigate unexpected patterns before accepting financial results. For demand-charge savings, inspect the intervals driving monthly billing peaks.
Translate insights into actions. Recommend a configuration, commercial terms, and approval conditions. Assign owners for procurement, engineering validation, financing, and operating controls. Identify assumptions that must become contractual commitments or measurable operating targets.
Test sensitivities and coherent scenarios. Vary equipment costs, weather, prices, degradation, and financing assumptions. Test combinations that could occur together. Where dispatch assumes perfect forecasts, compare less-informed operating assumptions before relying on the modeled benefit.
Align stakeholders and iterate. Ask engineering, finance, commercial, operations, and relevant regulatory specialists to challenge the case. Record unresolved issues, identify evidence needed to resolve them, and update the analysis before committing capital.
Where functions disagree on the preferred configuration, use structured investment decision support to reconcile assumptions, expose trade-offs, and establish approval conditions—not simply to select the highest reported return.
6. Example: System Advisor Model (SAM) in Action
Fictional example: Harborlight Energy Services is developing a customer-owned solar-and-storage installation for an industrial facility. The customer wants bill savings without paying for battery capacity that contributes little additional value.
The team compares three illustrative cases: one megawatt of solar alone; the same solar system with a 0.5-megawatt, one-megawatt-hour battery; and solar with a larger one-megawatt, four-megawatt-hour battery. The units of analysis are installation configurations behind the same meter, using identical financing and evaluation assumptions.
Inputs include interval consumption, the customer’s tariff, local weather, supplier quotations, battery degradation assumptions, and replacement costs. In this hypothetical analysis, the larger battery delivers greater gross bill savings, but the smaller battery produces higher NPV because additional storage capacity is insufficiently utilized. Less-informed dispatch assumptions reduce the apparent savings of both storage options.
The customer selects the smaller battery, subject to engineering validation and revised supplier pricing. Harborlight specifies the operating controls required to deliver the modeled savings. The CFO then uses capital expenditure prioritization to compare this project with other approved customer-site investments under a limited funding envelope.
7. Strengths and Limitations
Strengths
- Connects engineering and finance. Equipment performance becomes an explicit driver of project economics rather than a separate technical appendix.
- Supports consistent comparisons. Common assumptions make alternative configurations easier to evaluate and challenge.
- Exposes decision drivers. Repeated simulations reveal which uncertain inputs warrant better evidence or contractual protection.
These strengths follow from SAM’s linked performance and financial models and its multiple-simulation capabilities. They are particularly useful when engineering, commercial, and investment teams must agree on one project case.
Limitations
SAM produces conditional estimates, not guaranteed production or returns. A typical meteorological year is useful for representative modeling but does not, by itself, establish downside probabilities. Weather variability and other uncertainties require explicit treatment.
Storage results also depend on dispatch assumptions. Perfect-look-ahead options know future modeled conditions and can be more favorable than achievable operations. Treat their results as an analytical reference, not automatically as a realizable business case.
Do not infer permitting readiness, interconnection feasibility, safety compliance, or regulated cost recovery from an attractive financial result. Require separate evidence for each approval condition.
8. Common Pitfalls and How to Avoid Them
- Accepting defaults as evidence. Default values enable a starting simulation, not project validation. Maintain an input register with sources, dates, owners, and confidence levels.
- Using annual averages for time-sensitive value. Average prices or consumption can conceal tariff-driven economics. Use relevant time-series data and verify the billing calculation.
- Confusing power and energy capacity. Specify both battery discharge power and stored energy. Check that the proposed combination can support the operating schedule being evaluated.
- Double-counting storage benefits. Do not independently add every potential revenue or savings stream. Demonstrate that one feasible operating schedule can deliver the combined benefits.
- Ranking projects only by LCOE. For investment decisions, examine cash flows and the value of delivery timing, not just average production cost.
- Ignoring execution costs. Include project-specific development, connection, operating, and replacement assumptions where relevant. Make unresolved costs explicit rather than silently excluding them.
9. How System Advisor Model (SAM) Relates to Other Frameworks
Discounted cash-flow analysis
SAM supplies performance-linked financial outputs; discounted cash-flow analysis provides the investment lens. Use SAM to develop the project case, then reconcile it with the organization’s approval model and required financial perspective. PPA financial models already calculate NPV and IRR, so avoid constructing a second model with inconsistent assumptions.
Scenario planning
Use scenario planning before simulation to define coherent alternative conditions—for example, lower electricity prices combined with a changed operating strategy. SAM’s parametric and stochastic tools then quantify selected implications. A sensitivity changes an input; a management scenario should explain why a combination of changes could occur.
REopt optimization
REopt is a complementary optimization tool rather than a traditional consulting framework. Prefer it when the initial question is optimal behind-the-meter sizing and dispatch. SAM offers REopt integration for certain photovoltaic-battery configurations, allowing optimized sizing and operating schedules to inform subsequent simulation.
10. Key Takeaways
- SAM is a performance-and-financial modeling tool, not a conventional strategy framework.
- Compare complete project configurations, including ownership and commercial assumptions.
- Validate operating behavior before trusting investment metrics.
- Test uncertainty and achievable dispatch, not just an attractive base case.
- Convert results into approval conditions, accountable actions, and monitored operating targets.
11. FAQs About System Advisor Model (SAM)
Is SAM relevant to every energy and utility business?
No. Its direct relevance is strongest for supported generation, storage, and customer-sited energy technologies. Network planning and other utility decisions require additional analytical tools.
Can SAM determine the best battery size automatically?
It can compare battery sizes through repeated simulations. Certain behind-the-meter photovoltaic-battery configurations also offer REopt-based sizing and dispatch optimization. Check compatibility and the optimization objective before interpreting “best.”
What is the minimum useful data for a customer-sited project?
Start with a credible system design, resource data, costs, ownership assumptions, interval consumption, and the applicable tariff. Demand-charge analysis requires particular attention to load peaks, not just annual consumption.
Does a positive SAM result mean a project is ready for investment?
No. It means the modeled case is attractive under its assumptions. Investment readiness also requires validated engineering, commercial terms, financing, delivery plans, and evidence that material approval conditions can be satisfied.