Analyze Procurement Spend

What You Will Learn

You will learn how to use Gemini to classify procurement spend, identify supplier concentration, compare unit prices, and generate a first-pass list of savings opportunities.

Required Dataset

Use the Atlas_Procurement_Dataset.

Use these tabs:

Purchase_Orders

Suppliers

Supplier_Performance

Create three new tabs:

Spend_Analysis_Practice

Spend_Summary

Savings_Opportunities

Before You Start

Copy 50–100 rows from Purchase_Orders into Spend_Analysis_Practice. Include fields such as PO Number, Supplier Name, Item Description, Spend Category, Quantity, Unit Price, Extended Spend, Contracted Price, Approval Status, and Emergency Purchase Flag.

Add new columns for:

Standard Category

Price Group Key

Benchmark Unit Price

Estimated Savings

Opportunity Flag

Review Needed

Step-by-Step Instructions

Step 1. Ask Gemini to structure the analysis

Use this prompt:

Act as a procurement analytics consultant.

Use the Spend_Analysis_Practice tab.

Objective: Recommend a procurement spend analysis.

Focus on spend classification, supplier concentration, unit price comparison, contract leakage, emergency purchases, and savings opportunities.

Return recommended formulas, summary views, and caveats.

Step 2. Classify spend

Ask Gemini to standardize Spend Category into clean categories such as IT, Logistics, Facilities, Professional Services, MRO, Raw Materials, and Other / Needs Review.

Use Review Needed = Yes for unclear or low-confidence classifications.

Step 3. Analyze supplier concentration

In Spend_Summary, summarize total Extended Spend by supplier and category using SUMIFS, QUERY, or a pivot table.

Ask Gemini:

Identify top suppliers, fragmented spend, tail spend, and categories where supplier consolidation may be worth reviewing.

Step 4. Compare unit prices

Create a Price Group Key using item description, category, and unit of measure. For each group, compare unit prices against the lowest or average unit price.

Use:

=IFERROR(MINIFS(Unit_Price_Range,Price_Group_Key_Range,Price_Group_Key),””)

Estimate savings as:

=MAX(0,(Unit Price-Benchmark Unit Price)*Quantity)

Expected Result

You should have a procurement spend view showing category spend, supplier concentration, unit-price variance, and preliminary savings opportunities.

Check Your Work

Confirm that categories are standardized, supplier totals reconcile to total spend, unit prices are compared only for similar items, and savings are labeled as preliminary.

Optional Extension

Ask Gemini:

Create a savings opportunity pipeline from Spend_Summary and Savings_Opportunities. Include opportunity type, evidence, estimated savings, confidence, effort, risk, owner, and next step.

How to get started

1

arrow-down-blue

Tell us about your project

2

arrow-down-blue

Interview candidates

(We’ll provide bios within 48 hours on average)

3

Select your consultant and start work

Find a Consultant

or email us at: [email protected]