Setting Up the Restructuring Program

Setting Up the Restructuring Program

A restructuring only converts intent into results when it is managed like a mission‑critical program—with clear governance, disciplined cadence, transparent metrics, and empowered people who can cut through silos. Without that scaffolding even the best‑designed strategy drifts, deadlines slip, and scarce liquidity evaporates. This chapter lays out the practical architecture for launching and running a world‑class restructuring program, beginning with the governance skeleton that keeps every moving part aligned.

6.1 Governance Structure and PMO

Why Governance Matters
Restructuring compresses years of change into months. Decisions worth hundreds of millions of dollars may be taken on weekly calls; covenant clocks tick in real time; and multiple advisor teams produce terabytes of analysis that can overwhelm leadership. Governance provides the filter, the authority, and the rhythm so that energy flows to the highest‑value tasks instead of getting lost in meetings, PowerPoints, and e‑mail threads.

Core Layers of Governance

  1. Board Oversight
    The board (or a special restructuring committee of independent directors) sets strategic guardrails, approves major milestones—diagnostic funding, CRO appointment, debt‑for‑equity proposals—and ensures fiduciary obligations shift appropriately toward creditors if insolvency is plausible. Meetings move from quarterly to monthly deep dives, supplemented by ad‑hoc sessions when liquidity or legal triggers arise.
  2. Steering Committee
    Chaired by the CEO or CRO, the steering committee meets weekly. Members include the CFO, GC, COO, HR head, and the lead partners from financial and legal advisors. This body signs off on work‑stream budgets, resolves interdependencies, and acts on escalations that exceed work‑stream authority—usually anything that shifts timeline, scope, or cash impact by more than ±10 percent.
  3. Program Management Office (PMO)
    The PMO is the operational nerve center. Headed by a program director—often a senior manager seconded from finance or strategy plus an external PMO specialist—the office owns the integrated master plan, risk register, and KPI dashboard. It runs the critical‑path logic, pushes updates to stakeholders, and enforces “data hygiene” so every decision draws from one source of truth.
  4. Work‑Stream Teams
    Each major lever—liquidity, operations, capital markets, legal, HR, IT, communications—has a dedicated team led by an internal owner paired with an external subject‑matter expert. Work streams plan in two‑week sprints, report progress and blockers to the PMO twice weekly, and escalate issues that threaten timeline or value capture.

Designing an Effective PMO

Structure and Staffing

  • Program Director. Senior executive with decision authority; bridges board priorities and frontline execution.
  • Deputy Director. External PMO consultant ensuring best practices, tool adoption, and candid challenge.
  • Work‑Stream Liaisons. One analyst for each work stream validates data and synchronizes milestones.
  • Risk & Controls Lead. Monitors compliance, audit readiness, and change‑control discipline.
  • Communications Manager. Crafts stakeholder updates, aligns messaging, and maintains document repository.

Operating Cadence

  • Daily Stand‑ups. 15‑minute check‑ins with work‑stream leads to surface blockers early.
  • Weekly Steering Packet. Liquidity dashboard, milestone tracker, risk heat map, and “decisions required” list prepared by PMO and circulated 24 hours ahead.
  • Monthly Board Book. Scenario‑model refresh, covenant outlook, stakeholder status, and lessons learned; reviewed in two‑hour board sessions.
  • Quarterly Retrospective. Cross‑functional workshop to capture best practices, adjust governance charters, and recalibrate incentives.

Tools and Technology

  • Integrated Work‑Plan Software (e.g., Smartsheet, MS Project) with dependency logic visible to all teams.
  • Real‑Time KPI Dashboard updating liquidity, EBITDA run‑rate, cash burn, and work‑stream savings versus target.
  • Secure Data Room housing all models, legal documents, and advisor reports with role‑based access control.
  • Issue‑Tracker Log assigning owner, root cause, resolution path, and due date to every risk or blocker.

Decision Rights and Escalation Paths

Decision Type

Work‑Stream Authority

PMO Authority

Steering Committee

Board/Special Committee

Scope change ≤ 5 % budget

Approve / Execute

Notify

—

—

Cash impact > 5 % or timeline slip > 2 weeks

Recommend

Escalate

Approve

—

Debt issuance, asset sale, or equity raise

Recommend

Coordinate advisors

Approve term sheet

Ratify

Court filing or legal venue change

Inform

Coordinate counsel

Recommend

Approve

Risk Management Within Governance
The PMO maintains a live risk register scored by probability, impact, and mitigation readiness. Top‑10 risks feature on every steering agenda. Examples include: DIP covenant breach, union strike, IT system failure during ERP carve‑out, or regulatory delay on asset sale. Each risk has a named owner, contingency budget, and trigger points for escalation.

Common Pitfalls and Preventive Actions

  • Shadow Governance. Functional leaders create side committees that dilute accountability. Fix: enforce single‑point reporting through PMO and Steering.
  • Data Fragmentation. Multiple “final” models circulate, confusing creditors. Fix: impose version control and change‑log discipline; finance owns the master model.
  • Meeting Overload. Teams spend more time updating decks than executing. Fix: adopt tiered communication—daily stand‑ups, weekly packet, monthly deep dive—and ban slide revisions inside 24‑hour window.
  • Slow Decision Escalation. Blockers languish because thresholds are fuzzy. Fix: codify escalation triggers (cash variance, timeline slip, legal risk) and track response time KPIs.

Checklist—Governance and PMO Readiness

  • Have we published a governance charter with membership, cadence, decision rights, and escalation rules?
  • Does the PMO have authority to reallocate resources across work streams to protect the critical path?
  • Is every milestone in the integrated plan traced to a value driver and a liquidity forecast line item?
  • Do steering packets present metrics visually—RAG (red‑amber‑green) status—so decisions focus on exceptions, not data hunting?
  • Have we dry‑run crisis scenarios (missed payroll, vendor credit freeze) to test communication and decision speed?

When governance is architected with clarity, discipline, and agility, the restructuring program gains a backbone strong enough to carry the weight of complex decisions yet flexible enough to adapt as new information emerges. The PMO then becomes more than a reporting office—it is the engine room that propels the turnaround from aspiration to accomplishment.

6.2 Restructuring Charter and Mandate

A well‑crafted restructuring charter functions as the program’s constitution—codifying purpose, scope, decision rights, and success metrics in a single, authoritative document. Without it, work streams proliferate in conflicting directions, stakeholders argue over priorities, and critical deadlines slip in a haze of ambiguity. Drafting the charter is therefore one of the first—and most strategic—acts of the steering committee.

Purpose and Objectives: Setting the North Star
The charter begins with a concise statement of why the restructuring exists and what it will achieve. Typical objectives include: restore liquidity to a minimum of six months’ runway; achieve a leverage ratio ≤ 4.0× EBITDA within 18 months; lift normalized EBITDA margin by 300 basis points through operational improvements; and secure a sustainable capital‑structure solution—whether out of court or via a court‑approved plan—by a target date. Objectives must be SMART: specific, measurable, achievable, relevant, and time‑bound. Ambiguous aspirations (“improve competitiveness”) provide no guidance when trade‑off decisions arise.

Scope: What’s In, What’s Out
Scope clarity prevents scope creep and political turf wars. The charter lists in‑scope levers—liquidity management, operational turnaround, capital‑structure redesign, strategic portfolio decisions—and explicitly excludes initiatives better handled in steady‑state governance (e.g., regular product‑development cycles). For multinational groups, it specifies which legal entities and regions the program covers. Asset sales, plant closures, or IT overhauls exceeding a dollar threshold automatically fall under restructuring governance; minor facility upgrades do not.

Roles and Responsibilities: Defining the Chain of Command
The charter names the accountable leaders: board special committee chair, CEO, CRO, CFO, GC, HR head, and PMO director. It delineates RACI status (Responsible, Accountable, Consulted, Informed) for each major decision category—budget changes, legal filings, employee‑communication releases, and new‑money financing. This eliminates finger‑pointing and accelerates approvals.

Decision Rights and Escalation Protocols
Clear decision thresholds keep momentum. For example:

  • Cash disbursements over $5 million outside approved working capital require CRO and CFO joint sign‑off.
  • Asset disposals above $25 million or beyond 10 percent of production capacity escalate to the steering committee.
  • Legal venue changes (e.g., Chapter 11 filing) require board special‑committee approval.
  • Vendor‑payment moratoria longer than 10 days trigger immediate board notification.

The charter stipulates escalation timelines—issues left unresolved at a work‑stream level escalate to PMO within 24 hours and to steering if still unresolved 48 hours later.

Key Performance Indicators (KPIs) and Reporting Cadence
Metrics anchor accountability. The charter specifies weekly, monthly, and quarterly KPIs such as:

  • Minimum liquidity balance and variance vs. 13‑week forecast
  • Net working‑capital days and trend line
  • EBITDA run‑rate versus target trajectory
  • Realized versus targeted cost savings by lever (procurement, footprint, SG&A)
  • Capital‑structure milestones (waiver secured, exchange offer launched, DIP facility closed)
  • Employee‑engagement index and critical‑talent retention rate

It also defines the reporting cadence: a weekly RAG‑status steering pack, a monthly board book, and a quarterly investor or creditor update. Each report references the same single source of truth model maintained by Finance under PMO supervision.

Resource Allocation and Budget Authority
The charter authorizes a restructuring budget capturing advisor fees, PMO staffing, technology tools, and contingency reserves—for example, 2 percent of projected savings earmarked for program costs, capped at $50 million unless the board approves expansion. Work‑stream leads can redeploy up to 10 percent of their allocated funds without steering approval, preserving agility.

Guiding Principles and Cultural Norms
Beyond mechanics, the charter articulates behavioral expectations: data transparency over political positioning; bias for action over analysis paralysis; one‑team mindset across functions and advisors; and strict confidentiality until public‑disclosure triggers are met. Violations—such as leaking draft creditor term sheets—carry predefined consequences up to removal from the program.

Approval and Amendment Process
Adoption requires formal board resolution and, where mandated by governance bylaws, shareholder acknowledgment. Amendments follow a structured process: work‑stream lead proposes change, PMO assesses impact, steering reviews, and board approves if scope, budget, or timeline shift beyond predefined tolerances. This maintains flexibility without inviting chaos.

Launch Communication
On ratification, the charter is circulated company‑wide via CEO memo, posted on the internal portal, and reviewed in all‑hands meetings. Externally, a high‑level summary (objectives, leadership structure, expected timeline) is shared with creditors, regulators, and key vendors to signal professionalism and build confidence.

Charter At‑a‑Glance—Essential Sections

  1. Mission Statement & Objectives
  2. Scope Definition
  3. Governance Org Chart & RACI
  4. Decision Thresholds & Escalation Paths
  5. KPIs & Reporting Calendar
  6. Budget & Resource Authority
  7. Guiding Principles & Confidentiality Rules
  8. Amendment Protocol & Version Control

A restructuring charter drafted with this rigor does more than memorialize intentions—it operationalizes them. It becomes the touchstone every leader references when priorities collide, the yardstick by which progress is judged, and the anchor that keeps the program on course through turbulence.

6.3 Work‑stream Design and Staffing

The work‑stream architecture translates a high‑level restructuring plan into manageable packages of action and accountability. Each stream owns a discrete value lever—liquidity, cost, revenue, capital structure, legal process, talent, IT, communications—yet must plug seamlessly into every other stream through shared milestones and data. Designing and staffing these units is therefore less about drawing organizational charts and more about choreographing interdependent teams that move in the same rhythm.

Start with the Value Tree
Begin by decomposing the turnaround value case into its constituent earnings and cash drivers: working‑capital release, SG&A reduction, footprint rationalization, pricing uplift, debt reduction, and new‑money raises. Map each driver to a dedicated work stream. Resist the urge to replicate the legacy org chart; instead, align streams to outcome clusters, thereby cutting across functional silos. For example, a “Footprint and Asset Sales” stream might blend operations, real estate, legal, and tax specialists because all four capabilities determine timing and proceeds.

Define Mandate, Boundaries, and Success Metrics
Every stream charter should answer five questions:

1. What is the quantified target (e.g., $75 million annual SG&A savings, 20‑day reduction in net working capital)?
2. Which legal entities, regions, and processes fall inside scope—and which do not?
3. What is the deadline sequence—quick wins in 90 days, structural moves in 12 months?
4. Which data sources constitute the “official” baseline and how will variances be measured?
5. Who holds decision rights on scope changes, budget, and staffing?

Publishing these charters in the PMO portal eliminates duplication and clarifies handoffs.

Select the Right Leadership Pairing
Each stream is co‑led by an internal executive who owns the P&L impact and an external expert whose toolkit accelerates delivery. Pairing matters: an operations VP with plant‑closure experience partners well with a supply‑chain consultant skilled in Lean deployment. Both leaders report to the PMO director and attend weekly stream‑lead huddles where cross‑dependencies surface early.

Build a Balanced Team Composition
Aim for a 60:40 ratio of internal to external resources. Internal staff bring institutional knowledge, stakeholder credibility, and ensure capability transfer; external staff inject pattern recognition, velocity, and objective challenge. Typical roles include:

  • Value‑stream owner (internal)
  • Work‑stream manager (external or internal high‑potential)
  • Data analyst assigned from FP&A or treasury
  • Subject‑matter experts (tax, HR policy, procurement, IT) seconded part‑time
  • Change‑management and communications liaison to align messaging

Critical positions—such as cash‑flow modeler or data engineer—must be back‑stopped to avoid single points of failure. The PMO maintains a skills matrix so vacancies triggered by illness or attrition can be filled within 48 hours.

Adopt Agile Sprint Cadence
Streams operate in two‑week sprints with clearly defined deliverables: a revised demand forecast, a signed term sheet, a completed site visit, or a line‑level cost model. Daily stand‑ups keep blockers visible; retrospective sessions at sprint end capture lessons. The agile rhythm counteracts analysis paralysis and breaks mammoth tasks into digestible bites that show progress to anxious stakeholders.

Integrate Data and Tooling Early
Each stream receives a standardized toolkit: work‑plan templates, KPI dashboards, risk logs, and decision registers hosted on a shared digital workspace. Data flows into the central model through API connectors or controlled uploads, eliminating version confusion. Stream analysts tag every data point with source, timestamp, and owner for auditability.

Embed Change‑management Capability
Operational and financial fixes falter when cultural adoption lags. Allocate at least one change‑management resource per major stream to translate technical actions into frontline behaviors—new standard work, incentive tweaks, training modules. These specialists coordinate with HR and communications streams so messages and reward systems reinforce desired outcomes.

Align Incentives to Outcomes
Work‑stream leaders receive scorecards that blend immediate milestones (cash saved, tasks completed) with sustainability indicators (run‑rate variance three months post‑implementation). For internal leaders, tie a portion of annual bonus or retention grant to stream performance. For external advisors on gain‑share contracts, cap upside potential at a multiple of verified savings to protect economics.

Govern Handoffs and Dependencies
Many deliverables are predecessors for other streams: the IT team must migrate data before plant‑closure savings can book; a union‑negotiation outcome unlocks head‑count reduction. The PMO’s integrated Gantt chart flags these dependencies. Weekly steering reviews monitor “red line” tasks whose slippage jeopardizes downstream value. Stream leads come prepared with recovery plans for any task trending amber or red.

Checklist—Work‑stream Readiness

  • Does each stream have a written charter with quantified targets and timeline?
  • Are co‑leaders formally appointed, with clear division of internal vs. external roles?
  • Is a two‑week sprint backlog populated with tasks prioritized by value and dependency?
  • Have necessary data feeds and reporting dashboards been configured and tested?
  • Are change‑management and communications resources embedded, not bolt‑ons?
  • Does the PMO’s skills matrix identify backups for critical roles?

Designing and staffing work streams with this rigor converts abstract strategy into a living engine of coordinated action. The result is a restructuring program that moves in disciplined bursts, learns continuously, and delivers tangible value at the speed liquidity constraints demand.

6.4 Rapid 100‑Day Plan

Speed is the currency of restructuring. Creditors, employees, and customers do not judge progress by theoretical runway or elegantly worded strategies; they track real liquidity raised, costs removed, contracts renegotiated, and milestones hit. The rapid 100‑day plan provides the high‑velocity roadmap to convert restructuring intent into hard cash and irrefutable proof points—before skepticism metastasizes into revolt.

Purpose and Philosophy
The 100‑day window is long enough to enact meaningful change yet short enough to sustain urgency. It serves four objectives simultaneously:

  1. Stabilize the Core. Shore up liquidity, secure critical suppliers, and reassure key customers that operations continue without service degradation.
  2. Create Momentum. Deliver visible quick wins—inventory liquidation, SG&A cuts, price increases—that boost EBITDA and morale.
  3. Build Credibility with Creditors. Hit or exceed weekly targets so lenders and bondholders view management projections as bankable, unlocking flexibility on covenants and new money.
  4. Lay Foundations for Structural Moves. Complete diagnostics, option analyses, and stakeholder negotiations that enable deeper operational and strategic shifts in months 4‑18.

Design Principles

Time‑Boxed Phasing
While plans vary by industry and distress severity, an archetypal structure breaks into three overlapping phases:

  • Days 0‑30: Diagnostic & Immediate Action. Finalize 13‑week cash‑flow model, install daily cash war room, freeze discretionary spend, launch critical‑vendor outreach, and convene union or works‑council briefings.
  • Days 31‑60: Stabilization & Quick Wins. Monetize non‑core inventory, renegotiate top‑20 supplier contracts, implement temporary price surcharges where contractual leeway exists, and initiate zero‑based budgeting for SG&A lines.
  • Days 61‑100: Value Acceleration & Road‑to‑Yes with Creditors. Execute first plant consolidation or shift reduction, complete capital‑structure term sheet (waiver, amend‑and‑extend, or exchange), announce management incentive plan tied to 12‑month EBITDA targets, and launch strategic alternatives review for non‑core assets.

Outcome‑Centric Metrics
Every action rolls up to a quantified target: cash dollars in the bank, percentage points of margin lifted, debt maturities extended, or days of liquidity runway added. The PMO publishes a weekly “scoreboard” showing cumulative progress against plan; red cells trigger immediate root‑cause analysis and corrective measures.

Agile Execution
Work streams operate in two‑week sprints, as outlined in section 6.3, with sprint goals explicitly laddering into the 100‑day milestones. The cadence maintains adaptability—if a vendor negotiation stalls, the cost‑out team pivots to an alternate lever (e.g., freight consolidation) without losing momentum.

Critical Work‑Stream Deliverables

  • Liquidity & Treasury: daily cash variance reports, executed revolver draw or ABL upsize, finalized cash‑collateral control agreements.
  • Operations & Supply Chain: verified SKU rationalization list, Lean blitz results at pilot site, freight‑rate reductions locked via annual bid event.
  • Commercial & Pricing: net price‑realization tracker showing implemented surcharges and customer retention metrics.
  • Finance & Capital Structure: creditor presentations backed by live data room, term sheets circulated, covenant resets drafted.
  • Legal & Regulatory: drafted forbearance agreements, preliminary filing petition (kept “on the shelf”), labor‑law compliance reviews for announced workforce actions.
  • People & Communications: retention bonus matrix covering top 10 percent of critical roles, weekly town‑hall schedule, social‑media monitoring dashboard.

Governance and Reporting

  • Daily Liquidity Huddles (CFO, treasurer, PMO finance lead) for real‑time course correction.
  • Twice‑Weekly Stream Stand‑Ups to clear blockers and reallocate resources.
  • Weekly Steering Committee chaired by CEO or CRO to approve shifts in plan, budget, or timeline.
  • Bi‑Weekly Creditor Updates featuring cumulative progress, refreshed forecasts, and variance explanations.
  • Day 50 Midpoint Review with board special committee to validate plan trajectory, re‑sign liquidity assumptions, and green‑light phase‑2 initiatives.

Risk Mitigation

  • Supply‑Chain Shock: Maintain dual‑sourcing contingency list and pre‑approved rapid‑pay plan for any vendor that signals distress.
  • Labor Backlash: Coordinate with unions on change packages; secure “no‑strike” pledges in exchange for job‑security protocols.
  • Regulatory Delay: File preliminary notifications (antitrust, WARN) early; embed legal buffer days into schedule.
  • Execution Fatigue: Rotate sprint leads every four weeks; ensure rest cycles and recognition programs for frontline teams.

Checklist—Ready to Launch the 100‑Day Plan?

  • Has the board formally approved the plan objectives, milestones, and budget?
  • Are all work‑stream charters linked to day‑level timelines and quantified impact?
  • Is the real‑time KPI dashboard live and accessible to leadership and advisors?
  • Do critical external stakeholders—lenders, unions, regulators—have visibility into the first‑phase actions relevant to them?
  • Are contingency funds and decision rights clearly documented for mid‑plan course corrections?

The Payoff

A rapid 100‑day plan yields tangible dividends: cash balance moves from “weeks” to “months” of headroom; EBITDA upticks validate operational leverage; creditors gain confidence and soften terms; employees see a roadmap, not random crises. Most importantly, the company earns the strategic breathing room necessary to tackle deeper transformation without the ticking clock of imminent default.

Restructuring playbook

Request the Restructuring Playbook

How to get started

1

arrow-down-blue

Tell us about your project

2

arrow-down-blue

Interview candidates

(We’ll provide bios within 48 hours on average)

3

Select your consultant and start work

Find a Consultant

or email us at: [email protected]