Changeover Time

Goal of the analysis:

Measure, decompose, and reduce the time it takes to switch a line, machine, or cell from producing one product/recipe to another. Changeover Time is a primary lever for improving throughput, compressing cycle/lead time, increasing mix flexibility, and lowering unit cost without capex. A rigorous approach defines a consistent start/stop, separates internal (must stop equipment) from external (can be done while running) tasks, quantifies startup stabilization losses (first-article approval, time-to-rate, startup scrap), and applies SMED (Single-Minute Exchange of Dies) and standard work to remove, externalize, parallelize, and simplify steps. Executives use the analysis to raise OEE, enable smaller lots, stabilize schedules, and delay or avoid capital investments.

Data required:

  • Event timestamps and time studies:
    • Changeover start/end (policy: last good of previous → first good at steady-state rate for new SKU), setup/cleaning start/finish, first-article check, first-pass approval.
    • Step-level task logs or video-based time-motion with task codes (cleaning, tooling, fixture change, adjustment, calibration, recipe upload, purge, QA).
  • Internal vs external task classification:
    • Task catalog with internal/external tag, crew size, required skills/tools, opportunities for parallel work, pre-setup kitting readiness.
  • Tooling, materials, and readiness:
    • Tooling/stencil/die availability, presetting records, kit completeness for change parts, cleaning/chemicals readiness, recipe/parameter libraries.
    • 5S/visual controls, torque and calibration logs.
  • Quality and startup stabilization:
    • First-pass yield on first X units, startup scrap/rework, time-to-rate (time to reach target speed), deviations vs centerlines.
  • Scheduling and sequencing:
    • Changeover matrix (sequence-dependent durations by “from-to” recipe pair), planned vs actual setup times, frozen window/sequence adherence, average lot sizes.
  • Reliability and support:
    • Downtime during/after changeover (breakdowns, starved/blocked), PM calendar alignment, spares availability, MTBF/MTTR around setups.
  • People and skills:
    • Crew assignments, skill matrix/certifications, training records, shift differences, agency vs FTE flags.

Detailed step-by-step instruction on how to conduct the analysis:

  1. Standardize definitions and scope.
    • Define Changeover Time (CO): last good unit of product A → first good unit of product B running at steady-state speed and within spec.
    • Define supporting metrics: Internal Time, External Time, First-Article Time, Time-to-Rate, Startup Scrap %, Setup Adherence (planned vs actual), and Changeover Load % of shift.
  2. Capture and structure data.
    • Extract 8–12 weeks of changeover events from MES/SCADA; augment with time studies or video sampling on top pairs.
    • Build a step-level log per changeover with task, start/finish, crew, tools, internal/external tag; record readiness (kit complete Y/N).
  3. Compute baseline metrics.
    • By line and recipe pair: median/mean/P90 Changeover Time; Internal vs External share; First-Article Time; Startup Scrap %; Time-to-Rate.
    • Setup Adherence = Planned Setup Time ÷ Actual Setup Time; Changeover Frequency and total minutes per week; Changeover Load % = Setup minutes ÷ Available minutes.
  4. Build a sequence-dependent changeover matrix.
    • Matrix of “from-to” SKUs with median/P75 times; identify “bad neighbors” (long transitions) and quick-switch pairs; overlay lot sizes and frequency.
  5. Decompose time and identify losses.
    • Pareto of step categories: cleaning/sanitation, change parts/tooling, adjustments/calibration, paperwork/IT/recipe, waiting/searching, QA/first-article, warm-up/purge.
    • Tag ECRS opportunities: Eliminate, Combine, Rearrange (externalize/parallelize), Simplify.
  6. Apply SMED systematically.
    • Externalize: preset change parts off-line, pre-assemble kits, pre-heat/pre-calibrate, stage tools at point-of-use.
    • Parallelize: add second operator for internal steps; overlap cleaning and change-part install.
    • Simplify/standardize: quick-release clamps, guide pins, color-coding, one-touch fasteners; digital recipe management and centerline sheets.
  7. Stabilize startup and quality.
    • Define centerlines and parameter windows; implement first-article checks and recipe verification; reduce startup scrap via golden batch references and poka‑yoke.
  8. Re-sequence and plan.
    • Use the matrix to batch by family (e.g., light→dark, small→large), minimize high-cost transitions, and enforce frozen windows.
    • Model EPEI (Every Part Every Interval) improvements from reduced changeover times to justify smaller lots.
  9. Pilot, measure, and lock standards.
    • Run SMED pilots on top 3 “from-to” pairs; compare pre/post medians, internal share, startup scrap, and time-to-rate.
    • Document Standard Work, 5S locations, checklists, and visual cues; train and certify crews; update planned times and dispatch rules.
  10. Governance and integrity checks.
    • Audit internal vs external classification consistency; verify timestamps against video samples; ensure recipe/QA evidence is captured.
    • Monitor sustainability with control charts (Setup Time, Startup Scrap) and tiered daily reviews.

Format of the output of analysis:

  • Executive scorecard: median/P90 Changeover Time, Internal vs External %, Setup Adherence, Time-to-Rate, Startup Scrap %, Changeover Load % of shift, trend vs target.
  • Changeover matrix: sequence-dependent times by “from-to” SKU family with heatmap and frequency overlays.
  • Pareto and step breakdown: stacked bars of task categories and a loss waterfall (planned → external → internal → startup → steady-state).
  • Before/after SMED: comparative visuals and video stills; time-motion “spaghetti” map for tool/people movement.
  • Scheduling panel: recommended family batching, frozen window rules, and projected EPEI/lot-size impacts.
  • Action tracker: ECRS items, owners, due dates, expected minute reduction and verified results.

How to interpret results:

  • High Internal share (>60%) with long total time: Large SMED opportunity—externalize tasks (preset, pre-heat, pre-kit) and add parallel work.
  • High variability (P90 ≫ median): Inconsistent standard work or readiness; tighten 5S, kitting, and checklists; increase training and certification.
  • Short setup but long Time-to-Rate/high startup scrap: Parameter/centerline issues; strengthen recipe control and first-article process.
  • Sequence-dependent spikes: Re-sequence plan to avoid “bad neighbors,” increase family batching, and adjust lot sizes.
  • Large negative Setup Adherence (actual ≫ plan): Planning unrealistic or data outdated; update standards and schedule with demonstrated times.
  • Shift-to-shift differences: Capability or supervision gap; standardize training and embed visual controls.

Steps a company can take to improve on this measure:

  • SMED and method engineering:
    • Externalize tasks (preset change parts, pre-stage materials), implement quick-release mechanisms, color-code parts, and use fixed-stops/guide pins.
    • Parallelize with a second operator during internal steps; redesign tasks to eliminate waits.
  • Readiness and 5S:
    • Kitting for changeovers with completeness checks; shadow boards and point-of-use storage; digital checklists with sign-offs.
  • Recipe and quality control:
    • Digital recipe libraries, centerline sheets, first-article audits, and poka‑yoke on common mis-sets; SPC on startup CTQs.
  • Scheduling and policy:
    • Batch by family using the matrix; enforce 24–72h frozen windows; incorporate realistic planned setup times; use finite scheduling.
  • Reliability and support:
    • Align PM with changeover windows; ensure spare parts availability; calibrate tools routinely to prevent post-setup adjustments.
  • People and capability:
    • Certify operators on standard work; use video work instructions; conduct periodic SMED kaizens; recognize teams for sustained adherence.
  • Example scenarios:
    • If median changeover is 75 minutes with 70% internal, pre-kit and preset change parts and add quick-release clamps; target −40% time and internal share ≤50% in 6 weeks.
    • If P90 is 2× median due to missing tools, implement 5S, kit completeness checks, and a changeover cart; expect variability to halve within two cycles.
    • If startup scrap is 4% on dark-to-light transitions, re-sequence light→dark or introduce purge protocol and centerline audits; cut startup scrap by ≥50%.

Benchmark comparisons:

General benchmarks (directional):

  • SMED programs commonly achieve 30–50% reduction in changeover time within 8–12 weeks; world-class achieve single-digit minutes for certain discrete setups.
  • Internal share after SMED: ≤40–50% for many lines; best-in-class drives most tasks external and parallel.
  • Setup adherence: planned vs actual within ±10–20% in mature programs; startup scrap <1–2% after centerlining.
  • Changeover Load: in high-mix, keep total setup time ≤15–25% of available time for stable OTIF; use batching if higher.

Constructing internal benchmarks:

  • Track median and P90 changeover times and internal/external share by line and top 20 recipe pairs; publish quartiles and set guardrails (alert if P90 > 1.5× median).
  • Maintain and update the changeover matrix quarterly; require SMED review for any pair above target.
  • Pair changeover metrics with OEE, schedule adherence, lot size, and OTIF; prioritize pairs with high time and high frequency.
  • After engineering or tooling changes, re-time and reset planned setup standards; lock standard work with periodic audits.

How to get started

1

arrow-down-blue

Tell us about your project

2

arrow-down-blue

Interview candidates

(We’ll provide bios within 48 hours on average)

3

Select your consultant and start work

Find a Consultant

or email us at: [email protected]